Originally they thought they wanted to use the airform as the form for the edge […]
Tag: lake county
Wednesday, Aug 14, 2024 Removing bottom of spray block
Getting the bottom parts of the spray blocks for the porch openings out of the […]
Tuesday, August 13th, 2024 More Slab prep
They finished digging the tie beams and inset wall footing trenches. The Pest treatment was […]
Monday, August 12, 2024 Slab prep
Just a quick look around at the progress leveling/compacting the ground and digging trenches for […]
Tuesday, August 6th, 2024 Waiting for Slab
Monday the Crew came in and filled in the trenches in prep for putting in […]
Monday, August 5th, 2024 Hurricane Debby Day
Still not much to report here. Power out at building site and it is raining.Slab […]
Friday, August 2nd, 2024
Really nothing new to report. Plumbing inspection for the parts under the floor happened.
Thursday, August 1, 2024 Need Some One to do the Flat exterior walls.
So the Dome Shell is done but now we need to do those flat walls […]
Wednesday, July 31, 2024 In floor Plumbing
The Plumbing crew finally got back to us. Apparently who ever they sent to place […]
Tuesday, July 30, 2024 Just more underfloor Electric
Sorry no new videos or pictures today. Really nothing new to look at. I took […]