So the guys took a long weekend after the 4th of July which is why there hasn’t been any new progress to show since July 3rd. South Industries pretty much finished the structural rebar today. Some stub outs for the cut out walls/soffits and the augment walls still need to be done but structurally for the domes, it is ready. We had hoped to get the Electrician to get started on the low stuff last week but they didn’t show up to get started till today and then couldn’t get anything done because they didn’t have all their materials yet. So, I don’t believe that South Industries is going to start spraying any shotcrete tomorrow. The other project that needs to get done before any shotcrete gets near the cut outs is they need to finish all the bucks and spray stops for the augments and cutouts. They already placed the roof hatch buck since that affected the rebar.
Here are a few pictures of the Rebar to go with the video.